Code |
Meaning |
Description |
10 |
Original Baseline |
Used to reference the Original Baseline Version of Approved Budget Plan Type. |
100 |
Submitted Change Documents |
Used to reference the sum of Change Orders and Change Requests in the system with system status Submitted. |
110 |
Projected Total |
Used to reference the sum of amount of Current Working Version, Approved Change Documents, Submitted Change Documents and Working Change Documents. |
20 |
Change Documents from Prior Baseline Versions |
Used to reference the sum of impact amounts from all Change Documents included into all previous Baseline Versions of Approved Budget Plan Type. |
30 |
Adjustments from Prior Baseline Versions |
Used to reference the sum of all adjustments included into all previous Baseline Versions of Approved Budget Plan Type. |
40 |
Current Baseline |
Used to reference the Current Approved Baseline Version of Approved Budget Plan Type. |
50 |
Change Documents Included in this Version |
Used to reference the sum of Change Order amounts already included into the Current Working Version of Approved Budget Plan Type. |
60 |
Adjustments |
Used to reference the sum of adjustments already made to the Current Working Version of the Approved Budget Plan Type. |
70 |
Total Current Working |
Used to reference the sum of Approved Budget Current Working Version amounts. |
80 |
Approved Change Documents |
Used to reference the sum of Change Orders and Change Requests in the system with system status Approved. |
90 |
Working Change Documents |
Used to reference the sum of Change Orders and Change Requests in the system with system status Working. |