BLDG_COMPLETED |
Building Completed |
Structure completed; wiring, roof etc. |
COUNTY_INSP |
County Inspection |
Obtain occupancy permit from county inspection office. |
FALL_SEM |
Fall Semester |
Tuition, living expenses, books, etc. for Fall Semester. |
FIFTH_ADV |
Fifth Advance |
All work complete, final inspection, Use and Occupancy Permit. |
FIRST_ADV |
First Advance |
Installation of Foundation. |
FOURTH_ADV |
Fourth Advance |
Trim complete (ready for paint). |
LAND_CLEARED |
Land Cleared |
Land around the main site cleared of all trees, brush, etc. |
PERM_CONV |
Permanent Conversion |
Activities to convert construction loan to a permanent one. |
SECOND_ADV |
Second Advance |
Installation of Roof Sheathing (ready for Mechanical Trades). |
SINGLE_DISB |
Single Loan Disbursement |
Used for loans with single disbursements. |
SPRING_SEM |
Spring Semester |
Tuition, living expenses, books, etc. for Spring Semester. |
SUBDIV_PAVED |
Subdivision Paved |
Roads in development paved and topped. |
SUMMER_SEM |
Summer Semester |
Tuition, living expenses, books, etc. for Summer Semester. |
THIRD_ADV |
Third Advance |
Rough trades complete (ready for drywall). |