Code |
Meaning |
Description |
ACCRUED PAST FUNDS |
Failure 8 |
Revenue has accrued past allocated funds |
COMPLETE |
Success 1 |
Baseline generation complete |
FUND NE BUDGET |
Failure 6 |
Project funding does not equal total budget for project |
NO COST BUDGET |
Failure 5 |
This project requires a cost budget |
ORIG CREATED |
Success 2 |
Baseline generation complete - original budget created |
ORIG NOT CREATED |
Warning 3 |
Baseline generation complete - unable to create original budget |
PROJ FUND NO BUDGET |
Failure 4 |
Project funding exists without corresponding budget |
PROJECT EVENT EXIST |
Failure 9 |
Cannot baseline with Task Level funding since project level events exist. |
ROWS LOCKED |
Failure 7 |
Rows locked by another user |
TASK FUND NE BUDGET |
Failure 1 |
Task funding does not equal budget for one or more tasks |
TASK FUND NO BUDGET |
Failure 3 |
Task funding exists without corresponding budget |
TASK FUND PROJ BUDGET |
Failure 2 |
Task funding exists while budget is at project level |